Open Hearth Parking Garage
February 13, 2020
West Pike Street Facility
February 7, 2020

U.S. Department of Veterans Affairs

 

CPS was the Parking Garage Specialist on the construction of this two story, post-tensioned, cast-in place concrete parking garage.

Location: Erie, Pennsylvania
Client: U.S. Department of Veterans Affairs
Architect: Desman Associates
Contract Amount: $2,150,000
Completion Date: January, 2016

CPS was responsible for the structural excavation, concrete spread footings, backfill, sub-base, retaining walls, slab on grade slabs, and the elevated post-tensioned deck & crash walls. CPS made concrete pours in excess of 300 cubic yards to meet the schedule and post-tension placement requirements. CPS installed the cable barrier systems, sealants, expansion joints, waterproofing, and traffic bearing membrane coating system on this project. CPS also installed all of the concrete site work curbs and sidewalks which connected this new structure to the existing campus.