One Stop Center Garage
February 6, 2020
Canterbury Place
September 11, 2014

Medina Stadium

 

Located in an urban setting just 26 miles from Akron, this historic stadium needed emergency structural repairs prior to the busy football season.

Location: Medina, Ohio
Client: City of Medina
Engineer: Fanning Howey Associates
Contract Amount: $315,000
Completion Date: September, 2003

The repair work consisted of the following:

  • Partial-depth concrete floor repairs
  • Install custom expansion joints
  • Hot-applied waterproofing membrane installed on plaza deck and interior planters
  • Install drainage board and tapered insulation

The project consisted of repairing the structural slab and placing a new concrete topping throughout. Other site improvements included new aluminum bleachers, painting, architectural wall coatings, caulking and the installation of a pedestrian traffic membrane.

CPS was formally commended for our “beyond the call of duty” efforts to complete this project on the original timetable, even though the scope of work nearly doubled.